XMM-Newton Mission Status & Performance Indicator

31-Dec-2003
Revolution 0743

Observing Time Implementation Status as of Revolution 0743

Predicted end of Guaranteed Time

Priority A and B
AO1, AO2 & AO3 Revolution 0966
( 18-Mar-2005 )

Guaranteed Time Program

Priority A and B
Number of allocated targets 824
Allocated cumulative exposure time (ks) 18907.7
Number of successfully observed targets 811  (98.4%)
Successfully observed cumulative exposure time (ks) 18692.7  (98.9%)

Open Time Program - AO1

Priority A and B
Number of allocated targets 642
Allocated cumulative exposure time (ks) 14358.3
Number of successfully observed targets 624  (97.2%)
Successfully observed cumulative exposure time (ks) 13806.3  (96.2%)

Open Time Program - AO2

Priority A and B
Number of allocated targets 398
Allocated cumulative exposure time (ks) 12505.6
Number of successfully observed targets 386  (97.0%)
Successfully observed cumulative exposure time (ks) 12376.5  (99.0%)
Priority C
Number of allocated targets 375
Allocated cumulative exposure time (ks) 10834.0
Number of successfully observed targets 49  (13.1%)
Successfully observed cumulative exposure time (ks) 1291.1  (11.9%)

Open Time Program - AO3

Priority A and B
Number of allocated targets 602
Allocated cumulative exposure time (ks) 19364.1
Number of successfully observed targets 33  (5.5%)
Successfully observed cumulative exposure time (ks) 1364.5  (7.0%)
Priority C
Number of allocated targets 431
Allocated cumulative exposure time (ks) 13425.9
Number of successfully observed targets 0  (0.0%)
Successfully observed cumulative exposure time (ks) 0.0  (0.0%)

TOO Targets

Number of targets 70
Successfully observed cumulative exposure time (ks) 2497.0

The respective implementation priorities of the Open and the Guaranteed time programmes have been adjusted several times since launch by the Science Working Team. At its December 2001 meeting, the Science Programme Committee (SPC) of ESA recommended to accelerate the completion of the Guaranteed Time programme.

Operational efficiency indicators as of revolution 0744

Instrument Efficiency Breakdown over the past 6 months Evolution of efficiency since start of routine phase
PN PN, Efficiency breakdown over the past 6 months PN, Evolution of efficiency since start of routine phase
MOS 1 MOS, Efficiency breakdown over the past 6 months MOS, Evolution of efficiency since start of routine phase
RGS 1 RGS, Efficiency breakdown over the past 6 months RGS, Evolution of efficiency since start of routine phase

Legends are available for these PDF diagrams.

Data Processing and Distribution status as of 31-Dec-2003

Total number of Planned Observations in Routine Phase (revs 0103-0743) 3237
Total number of Performed Observations in Routine Phase 3041
Total number of Observation Data Files generated 2974
Total number of Pipeline/Data Products sets generated and distributed 2883

Turnaround (in days) between Data acquisition and final Data Products distribution (last Quarter)
Values in excess of 90 days usually indicate a problem analysing the data and/or that re-processing was required.
Data production delay

Details on the Observation Status can be found on the Observation & Data Processing pages.

Publications based on XMM-Newton data

For a complete up-to-date list of publications please check here.

XMM-Newton publications per quarter
As "submitted to" or "published in" refereed journals, derived from astro-ph.
Total publications as of 31-Dec-2003; 436
XMM-Newton publications per quarter
Please note; the large number of publications in the 1st quarter of 2001 is due to the release of the A&A special issue on XMM-Newton. The number of publications in the quarter at the time of issue is an underestimate.